IDB Invest, Engie close financing of 151 MW Calama wind farm in Antofagasta

Subscribe to our newsletter and get the latest news and business opportunities in your inbox

IDB Invest, a member of the IDB group, and Engie Energía Chile, sealed a financing of US$125 million to finance the construction, operation and maintenance of the Calama Wind Farm (151 MW) in the Antofagasta Region.

The financing, which has a 12-year term, is made up of three loan tranches: one from IDB Invest resources, for US$74 million; a second of US$15 million in financing from the Clean Technology Fund (CTF), and a third of US$36 million from the Chinese Fund for co-financing in Latin America and the Caribbean (China Fund). In addition, the multi-donor fund NDC Acelera administered by the IDB and funded by the Nordic Development Fund, Austria, the Netherlands and Sweden, financed the technical work accompanying the transaction.

List of the country updates

Country updates

  • February 10, 2021

    Sonnedix starts operation of 170 MWp Sonnedix Atacama Solar PV plant in Pica district

    Sonnedix Power Holdings Ltd has started the operations of the 170 MWp Sonnedix Atacama solar photovoltaic plant located on 450-hectare (1,112 acres) of land in the Pica district, Atacama Desert,...

    Read more
  • February 08, 2021

    Aggreko to deliver 25.9 MW hybrid solar and thermal system

    Aggreko has signed a contract with Gold Fields, global mining operator, to provide a total of 25.9 MW hybrid solar and thermal power solution to the Salares Norte open pit mine in Chile. This solution...

    Read more
  • February 05, 2021

    Ibereolica submits EIS for planned 1,171 solar and wind complex in Antofagasta

     Spanish developer Grupo Ibereolica Renovables has submitted an environmental impact study (EIS) for the proposed 1,171 MW renewable energy complex in the region of Antofagasta in Chile.&nbs...

    Read more
  • February 04, 2021

    AES submits EIS for the development of 114 MW Don Alvaro wind project in Los Angeles

    AES Gener has submitted an environmental impact statement for the development of a 114 MW located approximately 13 km west of the Los Ángeles commune, Biobío Region, Chile. Th...

    Read more
  • January 29, 2021

    Repsol, Ibereolica ship nacelles for 110 MW Cabo Leones III Wind Project in Atacama

    Repsol and Grupo Ibereólica Renovables have planned to operate with 189 MW of installed power, with the shipment from Bilbao of the main technology components of their wind turbines. The first...

    Read more