Solarpack has started to commercial operation of the 123 MW Granja Solar power plant in Pozo Almonte, Tarapacá Region, in the middle of the Atacama Desert
The Granja solar plant developed, built and operated by Solarpack has started injecting energy into the Chilean national electricity system on March 2. This represents a very important milestone for the Company, which generates energy in Chile through an operating fleet that totals 181 MW.
The project has an installed capacity of 123 MW and represents an investment of more than US$110 million. The project has long-term non-recourse financing granted by KfW Ipex-Bank for up to US$91 million.
Granja will sell its energy to Chilean power distributors through long-term sales contracts (PPAs), signed after being awarded in 2015 electricity supply tender held in the country with the most competitive price offered by a solar photovoltaic project until the date, contributing to the reduction of the energy supply price of Chilean households. The project has been connected 10 months in advance of the date of commencement of the PPAs, which will begin on January 1, 2021.
EIG Global Energy Partners, in partnership with Abengoa and Acciona, has installed a solar receiver for the 210 MW Cerro Dominador solar complex in the Atacama desert in Antofagasta, Chile.&...
Read moreAtlas Renewable Energy and DNB Markets have announced the private placement of a US$ 253 million bond, which was also certified as a green bond and had the participation of investors from the USA, Eur...
Read moreChilean power generator Colbun has applied for environmental approval to build the 719 MW/788 MWp Inti Pacha solar photovoltaic project in the Antofagasta region in Chile.
Read moreEnel Green Power has planned to deploy a 418 MW new PV pipeline in Chile. The company has submitted for environmental evaluation to Environmental Assessment Service (SEA). Enel will develop a 317 MW...
Read moreTranselec has signed two contracts for the construction and operation and maintenance of a transmission line that connects to Maintream's 156 MW Puelche Sur wind farm located in the communes of Frutil...