Neoen is nearing operation as it reached more than 90% completion of the Capella Solar, the 140 MW project involving two photovoltaic (PV) parks and battery storage facility in El Salvador.
The facility is scheduled to start commercial operation on April 1, 2020. Neoen is now working on the commissioning plan.
The Capella Solar PV project is composed of the Albireo I and Albireo II. Together, they generate enough electricity to power up 255,000 average households each year and account for 4% of the energy produced in El Salvador.
The project also includes a 3.3 MW/2.23 MWh lithium-ion battery system and a transmission line of 8.7 kilometers.
AES and Corporacion Multi Inversiones(CMI) have completed a 100 MW Bosforo solar photovoltaic project in El Salvador. The project has an investment cost of about US$160 million and composed of t...
Read moreVestas has received its first-ever order in El Salvador for the 54 MW Ventus wind park, which will be the country's first utility-scale wind park. The engineering, procurement, and construction (EPC)...
Read moreReal Infrastructure Capital Partners has inaugurated its three solar photovoltaic parks in El Salvador with a combined capacity of 43.62 MW. The solar projects - 10.16 MW La Trinidad, ...
Read moreEl Salvador prepared the way for the construction of its first wind project. The government signed a contract with Ventus SA de CV, in charge of constructing the 54 MW wind park located in Metapan, of...
Read moreNeoen is announcing that it has sealed financing for Capella, a 140 MWp solar photovoltaic project in El Salvador. The facility is wholly-owned by Neoen and is due to be commissioned in early 2020. F...