Genneia SA has successfully put 3 renewable power plants in Argentina into operation.
The facilities that were connected to the national grid are the following:
Genneia invested some USD 32.5 million for each solar plant and USD 80 million for the wind project. The 2 solar projects can generate electricity for 30,000 homes while the wind project can produce energy for more than 30,000 households.
Nordex SE, German wind turbine maker, received a follow-up order to supply 24 turbines of the AW132/3465 model for the Vientos Neuquinos wind facility. The order came from AES Corp...
Read moreThe government of Argentina signs contracts for the selected 2 solar projects in RenovAr Round 2 renewable energy auction programme. CAMMESA served as the power purchaser for the said projects includ...
Read moreArgentina's Ministry of Energy and Mines announced the inauguration of a solar PV project. Located in Catamarca, the project involves the development of a 22.5 MW photovoltaic solar plant....
Read moreThe Cauchari Solar Power Plant, in Jujuy, Argentina, set up in 3 parts, the Cauchari Solar I, II and III with 100 MW each for a total of 300 MW, is being expanded by another 200 MW. The total is...
Read moreYPF Luz has signed an agreement with GE Renewable Energy for the construction of Los Teros Wind Farm, located in Azul, Province of Buenos Aires. The construction will begin in November. The project wi...
Read more