Energiekontor AG has reached financial close on its 60 MWp Letschin solar photovoltaic park project located in the district of Märkisch-Oderland in the federal state of Brandenburg, Germany.
The project is expected to generate around 68 GWh of green electricity annually. This is enough to cover the average annual electricity demand of around 22,000 households and thus contributes to saving more than 50,000 tonnes of CO2 per year.
The Letschin solar park has a long-term private power purchase agreement (PPA) with a well-known German industrial company. Construction of the solar park is scheduled to begin during Q3 of 2024, with commissioning currently scheduled for Q1 of 2025. The current planning is to transfer the solar park into the company’s own portfolio after successful commissioning.