The Ministry of Electricity and Water Affairs of Bahrain has launched a Request for Proposal (RFP) tender for the development of grid-tied solar photovoltaic (PV) projects with a combined capacity of 72 MW AC installed across various sites in Sakhir under a Build Own Operate and Maintain (BOOM) scheme for 20 years.

The solar PV facilities will be constructed on the rooftops, car park shades, Electric Vehicle (EV) charging stations, and grounds of the Bahrain International Circuit, University of Bahrain, Bahrain International Exhibition & Convention Centre, and Al Dana Amphitheatre.

The deadline for the submission of documents to participate in the tender is on October 16, 2022. 

Tender information can be accessed on our business opportunity page here.  

List of the country updates

Country updates

  • November 26, 2019

    Teekay LNG to start operation of LNG project before 2020

    Teekay LNG Partners is set to begin the operation of the Bahrain LNG project before the end of 2019.  The project is developed under a Build-Own-Operate-Transfer (BOOT) model.  T...

    Read more
  • July 01, 2019

    ACWA consortium reaches financial close for Al Dur 2 IWPP

    The ACWA Power-led consortium has signed the final financing agreements for the US$1.5 billion, 1.5GW Al Dur Independent Power and Water Plant (IWPP) Phase II project in Manama, Bahrain. The project...

    Read more
  • January 24, 2019

    ACWA Power-led team bids lowest for 100 MW Askar solar project

    ACWA Power-led team, together with Mitsui & Co, Almoayeed, has put the lowest bid for the 100 MW solar photovoltaic project in Bahrain. The project is located in Askar landfill site in Bahrain's S...

    Read more
  • October 12, 2018

    PB for Bahrain's Al Dur 2 IWPP

    Two bids have been received by EWA from ACWA Power, and Sumitomo. In August, it was announced that ACWA Power (SIDEM as EPC contractor) had submitted the lowest offer for the Al Du...

    Read more
  • January 30, 2018

    The bid deadline for the project has been extended