Vestas has received an order to supply EnVentus turbines for two wind projects in the US totalling 189 MW, both owned by Algonquin Power and Utilities Corp. One project, Deerfield 2, is located in Michigan, USA and consists of 16 V162-6.2 MW turbines in 6.0 MW operating mode and one V150-6.0 MW turbine in 5.6 MW operating mode. The other project, Sandy Ridge 2, is located in Pennsylvania, USA and consists of 14 V150-6.0 MW turbines and one V136-3.45 MW turbine in 3.6 MW operating mode.
Both orders include supply and commissioning of the turbines, as well as a 10-year Active Output Management 5000 (AOM 5000) service agreement, designed to ensure optimized performance of the asset.
Turbine delivery for the orders begins in the second quarter of 2022 with commissioning scheduled for the fourth quarter of 2022.