Nordex to supply wind turbines for 120 MW Evrencik wind project in Kirklareli

Subscribe to our newsletter and get the latest news and business opportunities in your inbox

The Nordex Group has received an order to supply and install 27 N149/4.0-4.5 turbines for the 120 MW Evrencik wind farm, owned by Evrencik Elektrik. The contract also includes a Premium Service agreement with a term of 15 years.

Installation of the first turbines at the site in the province of Kirklareli in Eastern Thrace, with an average wind speed of 8 m/s at a hub height of 125 meters. The installation is scheduled to start by October 2020.

The annual yield of the 27 turbines in the Delta4000 series is calculated at around 534 GWh.

The Nordex Group will be supplying the rotor blades, anchor cages, towers and generators for the turbines.