GE Renewable Energy has been selected by Sanko Enerji to provide 12 Cypress units and 2 units of 3 MW for the 70 MW Guney wind farm Located in Bursa, Turkey.
The wind farm is expected to produce enough clean energy to power the equivalent 71,000 homes, save about 200,000 tons of CO2.
The construction and commercial operation of the wind farm is scheduled to start by the last quarter of 2020. GE’s scope of work will also include 10-year service agreements.
GE Renewable Energy will locally produce the revolutionary two-pieces wind turbine blades in its LM Wind Power’s Bergama site, Izmir, Turkey, where GE has more than 550 employees. At the end of April 2019, the site decided to invest another US$30 million to hire 300 new employees and build an extension, in order to set-up the site to produce this new two-pieces blade, set to be assembled to GE’s Cypress turbine. Towers will also be produced in the country.
The Nordex Group has received an order to supply and install 27 N149/4.0-4.5 turbines for the 120 MW Evrencik wind farm, owned by Evrencik Elektrik. The contract also includes a Premium Service agreem...
Read moreThe European Bank for Reconstruction and Development (EBRD) has approved the US$37 million loan to Alenka Enerji Uretim ve Yatirim for the development of the 72 MW extension project of the K...
Read moreThe Nordex Group has secured a supply order of thirteen N133/4.8 turbines, the strong-wind variant of the Delta4000 series for the 62.4 MW Mersinli wind project that will be built near Torbali, about...
Read moreNordex has received an order from its new customer Karayel Elektrik. The company is to install 16 N149/4.0-4.5 turbines for the 76.8 MW Vize-2 wind farm. The machines, from the Delta4000 series, will...
Read moreThe Nordex Group has received orders from Boydak Enerji in which Nordex will supply 21 N149/4.0-4.5 turbines with a rated capacity of 4.8 MW each for the Ömerli wind farm. On top of this, Boydak...
Read more