Chint Solar has commenced the construction of its 103 MWp Midden-Groningen solar photovoltaic plant located in the Netherlands. The company is working together with experienced contractors. Goldbeck Solar and Greencells will construct the solar park, ABB Netherlands will build the 33/110 kV private substation and the local company Alsema will realize the high voltage connection to the TenneT substation at Kropswolde.
During its operational lifetime, the solar park will offset more than 1639 kilotons of carbon emmission and will produce enough renewable energy every year to power 35.000 households.
The project is expected to be grid-connected by the end of 2019.