Chint Solar has announced that its 103 MWp Midden-Groningen Solar Park at Sappemeer is connected to TenneT’s high voltage grid network and commenced full operations.
The solar project has entered the construction phase in February 2019 and completed in October.
Chint Solar features 315.000 High-quality panels, produced by Chint Solar’s sister company Astronergy, on 117 hectares of land in the municipality of Groningen, in the northern part of the Netherlands. The solar park will be officially opened in 2020 and expected to supply renewable electricity to about 32.000 households.
Chint Solar acquired the project from Powerfield in early 2017, which started developing it in 2015.
Uniper has selected Alfen to supply a large-scale battery energy storage system connected to its hybrid power plant at the Maasvlakte in the Netherlands. The 10 MW (10 MWh) storage system will be depl...
Read moreJinkoSolar Holding Co., Ltd. has supplied an approximately 40 MW capacity of ultra-high efficiency Cheetah HC 60 solar modules for the Almelo Project in the Netherlands. The modules were install...
Read moreVattenfall and Siemens Gamesa Renewable Energy have agreed to extend the Hollandse Kust Zuid turbine supply to include zone one and two in addition to three and four.
Read moreMitsubishi Corporation (MC) and Chubu Electric Power Co., Inc. have been selected as the preferred buyers in a bid for the Dutch Energy Company Eneco. Through their joint establishment of a special pu...
Read moreEssent has agreed to acquire Dutch clean energy company Vandebron. Essent, a subsidiary of the Innogy, will pay an undisclosed sum provided the transaction is approved by the Netherlands Authority for...
Read more