AES Tiete Energia SA has ended the deal with Renova Energia SA for the sale of the 743 MW Alto Sertao III wind power complex plus a 1.1-GW wind project pipeline.
The two companies have failed to reach an agreement with regards to the commercial conditions of the sale that valued at BRL516 million (US$125.4 million).
The Alto Sertao III project is divided into two phases with 438 MW Phase A in the pre-operational stage and the 305 MW Phase B in the planning stage. Brazil’s power sector regulator ANEEL has previously blocked the planned transfer of Phase B to AES Tiete.
Renova is continuing its negotiation with the Brazilian Development Bank (BNDES) to extend for three more months the maturity of a loan that is scheduled for October 15, 2019. The loan was provided for the development of the works on the Alto Sertao III wind complex.
The Brazilian Development Bank (BNDES) has approved financing of BRL1.26 billion (US$312.4 million) to Engie's 360 MW phase of Umburanas Wind Complex. The 360 Mw phase of the Umburanas Wind Power Com...
Read moreVoltalia wins new long-term power purchase agreements in Brazil during the public auctions organized by the national regulator for a 32 MW (solar) and a 16 MW (hydro) capacity. The Solar Serra...
Read moreEnel Brasil, a unit of Enel Group, is set to complete the takeover of the Brazilian distribution company Enel SP, formerly known as Eletropaulo, through the acquisition of the remaining stakes it...
Read moreCompanhia Paranaense de Energia (COPEL), in consortium with its subsidiary Cutia Empreendimentos Eólicos, has participated in the A-6 new energy generation auction in Brazil, having sold 14.4 a...
Read moreCanadian Solar Inc has been awarded three solar photovoltaic (PV) projects totaling 393.7 MWp in two recent Private Corporate Auctions held in Brazil in the third quarter of 2019. Canadian...
Read more