Yunneng Wind Power Co Ltd. has said that all 80 wind turbine foundations, including both the monopiles and transition pieces, have been installed at the 640-MW Yunlin wind farm located in the Taiwan Strait, between 8 and 17 km off the west coast of Taiwan.
The construction of the wind farm has completed the installation of all 80 underwater foundations, 68 wind turbines (with 52 already connected to Taipower's grid), 56 array submarine cables, and all 12 output submarine cables. Spanning 82 sq km, the wind farm's 640 MW capacity will supply clean energy to over 600,000 households. Power is delivered to Taiwan Electric Power Company through two onshore substations under two 20-year power purchase agreements.
The project is owned by Germany’s Skyborn Renewables, France’s TotalEnergies, Thai power producer EGCO Group and Japanese trader Sojitz. With 68 wind turbine generators installed, 52 of them already in operation, the project now enters into the final installation phase and remains on track for full completion by the end of 2024.
CSBC-DEME Wind Engineering has successfully installed the first offshore substation (OSS) topside at the 1044 MW Hai Long Offshore Wind Farm located in Taiwan Strait, Taiwan.
Read moreØrsted has appointed ABL to provide marine warranty survey services (MWS) for the 920 MW Greater Changhua 2b and 4 offshore wind farms in Taiwan.
Read moreTurbine installations have recommenced at the 640 MW Yunlin offshore project located in the Taiwan Strait approximately 8 km west of the coast of Yunlin County in Taiwan.
Read moreThe 1,022 MW Hai Long Offshore Wind Project located in Taiwan Strait, Taiwan has announced the official launch of offshore construction.
Read moreHsinyuan Wind Power Co. Ltd, a subsidiary of wpd, and Bank SinoPac have closed the financing for wpd’s Hsinyuan wind farm in Taiwan.
Read more