Turbines installed for 1.2 GW Offshore Wind Farm in Poland

Subscribe to our newsletter and get the latest news and business opportunities in your inbox
Turbines installed for 1.2 GW Offshore Wind Farm in Poland

ORLEN has announced that five turbines, each with a capacity of 15 MW, have already been installed for the 1.2 GW Baltic Power Offshore wind farm in an area of approximately 131 km2, located about 23 km north of the Baltic coastline, near Łeba and Choczewo in Poland. 

The first Polish offshore wind farm, jointly developed by ORLEN and Northland Power, can provide enough power to charge nearly 18,000 electric vehicles when operational.

The installation of each turbine at sea is preceded by the deployment of monopile foundations and transition pieces – a stage of the project that is now nearing its halfway point. Next, work will begin on laying subsea inter-array and export cables, followed by the installation of offshore substations in the autumn. Offshore installation works are expected to be completed next year. The subsequent stages will include testing and obtaining the necessary certifications and permits.

List of country news

Country news

  • August 01, 2025

    Siemens Gamesa to supply turbines for 400 MW Offshore wind farm in Poland

    Ocean Winds has signed contracts for the supply of wind turbines and a service maintenance agreement for its 400 MW BC-Wind project.

    Read more
  • April 03, 2024

    Substation contract awarded for 1.5 GW Offshore wind farm in Poland

    Seaway7 has announced the award of a sizable contract by PGE Polska Grupa Energetyczna and Ørsted for the transport and installation of the substations for the Baltica 2 wind farm, offshore Poland.

    Read more
  • March 04, 2024

    Ørsted signs Cable contract for 1.5 GW Offshore wind project in Poland

    PGE and Ørsted joint venture has signed contracts with Navantia-Windar and Orient Cable (NBO) for delivery of foundations and array cables for 1,500 MW Baltica-2 Offshore Wind Power Plant located in Poland. 

    Read more
  • February 15, 2024

    Van Oord to install monopiles at 1.5 GW Offshore wind farm in Poland

    Van Oord has been contracted for the transportation and installation of monopiles at Orsted and PGE's 1500 MW Baltica 2 Offshore Wind Farm in Poland. 

    Read more
  • January 22, 2024

    Construction Contractor selected for 1.5 GW Offshore Wind Farm in Poland

    PGE Group and Ørsted signed an agreement with GE Vernova and Polimex Mostostal for the construction of Baltica 2 Offshore Wind Power Plant in the Pomerania region of Poland.