Terna Energy to start construction of 680 MW pumped hydro storage project in October

Subscribe to our newsletter and get the latest news and business opportunities in your inbox

Greek renewable power producer and energy developer Terna Energy has reached the final investment decision (FID) for the planned pumped hydro storage project that will be located in the northwestern part of Aetolia-Acarnania in Greece. The project is scheduled for construction in October with target commissioning in 2025. 

The pumped hydro storage project has a capacity of 680 MW in turbine mode and 730 MW in pumping mode. The pump system will be installed underground at the existing reservoir of the Amari river dam and will have three constant speed turbine pumps of 31 MW each and twelve variable speed pumps of 3.2 MW each. The project represents EUR500 million (US$606.80 million). 

The upper reservoirs Agios Georgios and Pyrgos and common lower reservoir lake Kastraki will be used by the plant. The equipment for the project will be installed in two separate powerhouses on the northeastern bank. Pyrgos reservoir is predicted to be 285 meters high from the lower reservoir and Agios Georgios is about 238 meters higher than the Kastraki lake.

The excess energy produced from wind, solar, and thermal power plants will be used in the project.  The section in Agios Georgios reservoir will have four units with 460 MW in total in turbine mode and 496 MW in pumping mode while the Pyrgos reservoir will have capacities of 220 MW and 234 MW. The annual output is seen at 816 GWh.

List of the country updates

Country updates

  • May 03, 2021

    Hellenic cables to install subsea connection for 330 MW Offshore wind farm in Greece

    Hellenic Cables has been selected by TERNA ENERGY S.A, following an international tender, for the design, manufacturing, supply and installation of the 150 kV submarine cable system which will connect...

    Read more
  • April 07, 2021

    Completion of the submarine interconnection project between Crete and Peloponnese peninsula

    Prysmian Group and Independent Power Transmission Operator (IPTO) have announced the completion of the submarine interconnection project between the island of Crete and the Peloponnese peninsula, in G...

    Read more
  • March 31, 2021

    PPC to begin pre-construction of 200 MW portion of Kozani solar PV project in west Macedonia

    Development of a major-scale 200 MW solar farm planned by PPC Renewables in Ptolemaida, northern Greece, a project budgeted at EUR110 million (US$129.5 million), is expected to begin in approximately...

    Read more
  • March 12, 2021

    European Investment Bank to finance USD1.19 billion Interconnection project in Greece

    The Independent Power Transmission Operator announces the participation of the European Investment Bank (EIB) in the financing of Crete-Attica interconnection, a project with a total budget of EU...

    Read more
  • March 12, 2021

    IPTO, Sunlight to build 20 MW energy storage facility in Thiva

    Greek utility operator IPTO is partnering with Sunlight, a unit of Olympia Development Group, to build a 20 MW/20 MWh energy storage facility in central Greece.  The Memorandum of Understan...

    Read more

Share this update