Sterlite Power has signed the Concession Agreement for batch 13 that the company has won during auction No. 04/2018. The agreement was finalized during the first technical management meeting with ANEEL’s Superintendency of Concessions, Permissions and Authorizations for Transmission and Distribution (SCT).
The batch 13 includes the construction of 3 energy transmission lines, for a total length of 316 km, two substations and 1,544 MVA transformation capacity, with Annual Allowed Revenue (RAP) of BRL 74.72 million and an investment of BRL 777.8 million.
The project is expected to be completed in March 2023.