Sertum Energy Namibia completes the 5 MW portion of 27 MW Trekkopje Solar Project solar project in Namibia

Subscribe to our newsletter and get the latest news and business opportunities in your inbox

Sertum Energy Namibia has completed the development of a 5 MW portion of a 27 MW solar project located in at the Orano Trekkopje Mine, in the Erongo Region, Namibia. The project has been inaugurated and has a total investment of NAD120-million (US$7.9 million)

Sertum Energy Namibia, owner of the project, is a partnership between local businessman Elton Katangolo and Italian renewable energy sector player Enertronica SpA. Sertum Energy has signed a 25-year power purchase agreement with NamPower as part of the feed-in-tariff program.

List of the country updates

Country updates

  • July 05, 2018

    SunEQ Namibia announces financial close for 5 MW of solar photovoltaic facility

    SunEQ recently announced it has reached financial close for a 5MW solar photovoltaic project in Namibia. The facility will be built in the Otjozondjupa region for Ohorongo Cement; also...

    Read more
  • April 11, 2018

    The World Bank’s Multilateral Investment Guarantee Agency (MIGA) is guaranteeing USD 15 million non-shareholder loans from Investec Bank and USD3 million equity from Cigenco SA to support the construction, operation and maintenance of the solar project including the Ejuva One

  • April 11, 2018

    The World Bank’s Multilateral Investment Guarantee Agency (MIGA) is guaranteeing USD 15 million non-shareholder loans from Investec Bank and USD3 million equity from Cigenco SA to support the construction, operation and maintenance of the solar project including the Ejuva Two

  • March 15, 2018

    Alten Energias Renovables has reached financial close of the project

    Alten Energias Renovables has reached financial close of the project. Over US$50 million has been provided by the South African Standard Bank and Proparco, the private sector financing arm of Agence Francaise de Developpement (AFD)

  • March 14, 2018

    The solar park has been completed

    The solar park has been completed. The power will be purchased under a 25 year REFIT contract at the rate of NAD1.37 ($0.10) per kWh

Share this update