Podveležje wind farm project presented in Mostar by EP BiH

Subscribe to our newsletter and get the latest news and business opportunities in your inbox

EP BiH organized a presentation of its project to build the 48 MW Podvelezje wind park project​ located in Mostar, Bosnia’s Muslim-Croat Federation.

The project was split into three stages, the first of which is underway. The first stage is to draw up construction plans, procure 15 turbines of up to 3 MW and build the foundations and accompanying infrastructure for the wind farm. The second stage will see the construction of 30 110 kV substations and lay a high voltage cable along with a grounding network while the third stage will see the construction of local roads and platforms.

List of the country updates

Country updates

  • March 13, 2018

    EP HZHB has brought the wind farm online

  • February 21, 2018

    Siemens Gamesa supplies the turbines for the wind farm

  • February 01, 2018

    IFS Solar is developing the project after the concession contract has been awarded

  • January 30, 2018

    Serb Republic has signed a cooperation protocol with local company Timemedia and Goldwater towards the construction of the biorefinery

  • December 08, 2017

    Serb Republic will sign a cooperative agreement with the developer for the construction of the project

Share this update