Neoen SA commissioned the 81 MW wind farm located near the town of Närpes, west of Finland. The project consists of 18 Nordex N149 turbines, with a 4.5 MW capacity each.
For the total of EUR 85.4 million (US$96 million) investment cost project, EUR 66.5 million (US$75.61 million) was a senior debt provided by KfW Ipex and SEB.
Neoen holds the 80% stake in the facility alongside Prokon Finland, which holds the remaining 20%.
The Hedet wind project will deliver all its output to Google’s data center at Hamina in Finland, under a 10-year power purchase agreement.
VSB is developing the Juurakko wind farm located in the northern Ostrobothnia region of Finland near the town of Kalajoki. Nordex will supply its 5 MW onshore wind turbines for the 40 MW facility. Th...
Read moreThe Nordex Group has received an order from ABO Wind for the supply and installation of nine N149/4.0-4.5 turbines for the Finnish wind project Kokkoneva. The turbines will be supplied in the 4.8 MW o...
Read moreAquila European Renewables Income Fund (AERIF), advised by Aquila Capital, has approved the signing of a Sale and Purchase Agreement (SPA) to purchase approximately 14% of the equity in a Norwegian 40...
Read moreNeoen is set to build the Yllikkälä Power Reserve One, a new 30 MW energy storage plant with a storage capacity of 30 MWh near Lappeenranta in the south-east of Finland. The facility...
Read moreFortum has completed the sale of its 80% interest in the 500 MW Nordic wind portfolio to funds advised by Credit Suisse Energy Infrastructure Partners (CSEIP). The wind portfolio consists of Nyg&arin...
Read more