Neoen SA commissioned the 81 MW wind farm located near the town of Närpes, west of Finland. The project consists of 18 Nordex N149 turbines, with a 4.5 MW capacity each.
For the total of EUR 85.4 million (US$96 million) investment cost project, EUR 66.5 million (US$75.61 million) was a senior debt provided by KfW Ipex and SEB.
Neoen holds the 80% stake in the facility alongside Prokon Finland, which holds the remaining 20%.
The Hedet wind project will deliver all its output to Google’s data center at Hamina in Finland, under a 10-year power purchase agreement.