Lightsource bp has secured a AUD330 million (US$255.62 million) financing package and begun construction on its 107 MWdc West Wyalong and 214 MWdc Woolooga solar projects, located in New South Wales and Queensland.
Financing for the projects was secured from EDC, ING, Intesa Sanpaolo, and Westpac. Lightsource bp was advised on the projects by Macquarie Capital and King & Wood Mallesons.
Combined, West Wyalong and Woolooga will produce approximately 673GWh of renewable electricity a year, enough to power nearly 100,000 homes and offset 540,000MT tonnes of CO2 emissions.
The project is expected to be operational by the middle of 2022.
CIMIC Group’s UGL has secured a contract for the design, construction, and installation of a high voltage transmission line from Kidston to Mt Fox in Queensland, and a new 275kV switching statio...
Read moreElecnor has signed a turnkey contract (EPC) with the Australian group Clough to build the EnergyConnect project in Australia.
Read moreRayGen Resources Pty Ltd has completed an AUD42 million (USD$32.5 million) funding for the development of the concentrating photovoltaic (PV) solar co-generation tower with its electro-thermal storage...
Read moreHydrostor Inc, in partnership with Australian advisory firm Energy Estate, plans to build a 200 MW Advanced Compressed Air Energy Storage (A-CAES) project in Broken Hill, New South Wales for an invest...
Read moreThe New South Wales Government is asking generation, storage, and network developers to register their interest in being part of the State’s second Renewable Energy Zone in New England (New Engl...