Final wind turbine installed at Formosa 1 in Taiwan

Subscribe to our newsletter and get the latest news and business opportunities in your inbox

Formosa 1 has announced the complete installation of all 20 wind turbines for phase 2 of the project. Formosa 1 is the first commercial-scale offshore wind farm in Taiwan and will be able to supply 128,000 households with clean power.

The offshore construction of Formosa 1 Phase 2 started in May 2019, and the first wind turbine was hoisted into position on 24 July. The Formosa 1 project team overcame the challenges caused by four typhoons and other weather impacts and completed all wind turbine installation work this week. All the wind turbines are gradually entering the commissioning phase, and the project is expected to reach commercial operation by the end of the year.

A total of twenty 6MW wind turbines have been installed for Formosa 1 Phase 2. The installation work was carried out by three major subcontractors, including JDN for foundation and cable installation; Siemens Gamesa for wind turbine installation, operation and maintenance; and Fortune Electric for onshore electrical systems. More than 100 experts participated in the Formosa 1 Phase 2 project and construction teams.

The Formosa 1 project is a joint venture between Ørsted (35%), JERA (32.5%), Macquarie Capital (25%), and Swancor Holdings (7.5%).