Aker Solutions, Siemens sign contract for 1.4 GW East Anglia 3 offshore wind project

Subscribe to our newsletter and get the latest news and business opportunities in your inbox

Aker Solutions, in a consortium with Siemens Energy, has signed a contract with ScottishPower Renewables with the intention to provide the HVDC (high-voltage, direct current) converter stations for the East Anglia 3 offshore wind project in the UK.

East Anglia 3 is the second project to be developed in the East Anglia Zone, following the commissioning of East Anglia 1 in 2020. East Anglia 3 is located in the North Sea off the east coast of England and is planned for an installed capacity of up to 1,400 MW. It is part of the overall East Anglia Hub development which includes East Anglia 2 and East Anglia 1 North, with a planned total capacity of up to 3,100 MW. Planning applications for East Anglia 1 North (800 MW) and East Anglia 2 (900 MW) are currently being examined by the UK Planning Inspectorate.

Aker Solutions will not book order intake at this stage. Order intake is subject to the project reaching financial close in 2022. Aker Solutions’ first step in the scope will be the detailed design engineering, which will be executed by the company’s engineering office in Reading, UK.

Share this update