ACCIONA Energía completes wind turbine installation for Forty Mile Wind farm

Subscribe to our newsletter and get the latest news and business opportunities in your inbox

ACCIONA Energía has completed the wind turbine installation for the 280 MW Forty Mile Wind project in Bow Island, Alberta, Canada.

The company has now connected 14 of the 49 turbines to the grid, corresponding to 80 MW, meaning they are already supplying clean electricity for Alberta. The project consists of 49 5.7MW capacity Nordex wind turbines, each with a tower height of 108 m. With a total installed capacity of 280MW. Upon full energization, the wind farm will generate enough clean energy to power more than 85,000 homes. Electrical commissioning is ongoing, and the wind farm will be fully operational in spring 2025.