The Danish Energy Agency has prequalified a total of six consortia and companies to participate in the tender for Denmark's largest offshore wind farm to date "Thor Offshore Wind Farm" with a capacity of minimum 800-1000 MW.
There will be competition to build Denmark's largest offshore wind farm to date, which will be located in the North Sea off the coast at Thorsminde.
The selected applicants are the following:
The Danish Energy Agency will complete the tender in 2021. The decision on the winner of the tender is expected to be announced at the end of 2021.
The total investment costs for Thor are estimated at a total of DKK 15.5 billion (USD2.529 billion). The grid connection of the first turbine can take place from January 1, 2025, and Thor must be fully established and connected to the grid by the end of 2027 at the latest.