The Danish Energy Agency has launched the tendering process for the planned Thor Offshore Wind Farm project. Thor will be Denmark's largest offshore wind farm to date with a capacity of 800-1000 MW when it is fully established and connected to the grid by 2027 at the latest.
The publication of the contract notice and the tender material kick-starts the tender process for Thor Offshore Wind Farm. The process initially includes a pre-qualification phase where the Danish Energy Agency identifies the companies with sufficient financial and technical capacity to participate in the tender. This is followed by a negotiation phase with the pre-qualified bidders that potentially may lead to adjustments in parts of the tender with an aim to lower the bid price.
The tender model for Thor follows the same process as previous Danish offshore wind tenders which have achieved historically low prices internationally. The published tender material contains the tender conditions as well as a pre-qualification document, a draft concession agreement, and all necessary licenses, etc. Together with the ongoing preliminary studies of the area for the wind farm, the aim is to make it easier for the tenderer to provide a cost-effective bid for the offshore wind farm.
As something new, the tender includes the offshore grid connection, including the offshore substation, landing cables, and a high-voltage onshore substation as well as flexible size of the park between 800-1000 MW. This will allow bidders to optimize the dimensions of export cables and wind farm capacity, thus making the overall solution as cost-effective as possible.
The deadline for application for prequalification is no later than December 1, 2020, and potential bidders will in the period from the 1 October to the 16 November 2020 be able to ask questions in writing to the Danish Energy Agency about the tender.
The final tender deadline for the tender is expected to be 8 November 2021. The schedule and process are described in more detail in the tender material.
The tender information can be accessed on our business opportunity page here.
Danish energy company Better Energy has started the construction of a new subsidy-free 200 MW solar PV project in Denmark. Heartland is the owner of the plant. Better Energy will be responsible for developing, building and operation of the plant.
Read moreThe construction phase of the Viking Link Interconnector project, a high-voltage direct-current (HVDC) link between the UK and Denmark, has commenced with Siemens Energy Ltd mobilizing to the site to start the construction of the first stage of works, a 2.4 km long access road for the Bicker Fen converter station site.
Read more1,400 MW Viking Link Interconnector between Denmark and the UK gets support from SACE Export Credit and Euler Hermes Export Credit through the first-ever multi export credit agency (ECA) covered green loan.
Read moreA consortium, consisting of three of the largest Danish pension and energy companies - PensionDanmark, PFA, and SEAS-NVE, is ready to finance and operate an upcoming energy island called VindØ to be located in the North Sea. In the long term, VindØ can be the base for up to 10-gigawatt offshore wind turbines, corresponding to approximately 25 traditional offshore wind farms.
Read more
Europe connected 3.6 GW of new offshore wind capacity in 2019 according to the report by WindEurope released today. This is a record in annual installations.
Read more