Vestas has received a 36 MW repowering order for the Overgaard II wind project from Wind Estate A/S. The order is derived from Denmark’s second energy-neutral auction in 2019.
The firm order includes supply, installation and commissioning of ten V126-3.45 MW turbines delivered in 3.6 MW Power Optimised Mode, as well as a ten-year Active Output Management 5000 (AOM 5000) service agreement. The ten new Vestas turbines will more than double the wind park’s energy production by replacing the current site’s eight 2 MW NEG Micon turbines.
The order comes two months after Vestas announced the order for the final phase of the 94 MW Overgaard I wind project. Once the 130 MW site is fully completed, it will make up Denmark’s largest onshore wind farm.
Deliveries are expected to begin in the third quarter of 2021, while commissioning is planned for the fourth quarter of 2021.
Gazprom, the project developer of Nord Stream 2 gas pipeline under the Baltic Sea, has planned to complete the construction of the scheme without the help of foreign companies. Last month, the&n...
Read moreEurope connected 3.6 GW of new offshore wind capacity in 2019 according to the report by WindEurope released today. This is a record in annual installations.
Read moreThe Government of Denmark, through the Danish Energy Agency (DEA), has approved the development of the 604.8 MW offshore wind farm in Baltic Sea. DEA has consented and issued an envir...
Read moreTekmar Energy Limited, a Tekmar Group Company, has been awarded by Global Marine Group and JDR Cables for the supply of TekLink® cable protection systems and cable hang-off assemblies for Danish K...
Read moreEurowind Energy A/S has announced the acquisition of SE Blue Renewables. SE Blue Renewables was established in 2013 when PFA and SE (today a part of Norlys) bought DONG Energy's Danish onshore wind...
Read more