CWP Renewables and Partners Group have secured a AUD113 million (US$85.5 million) senior debt facility for the 135 MW Crudine Ridge wind farm, located near Mudgee in New South Wales. Th...
Read moreVestas will supply and commission the turbines for the project. Turbine deliveries are scheduled for the second quarter of 2019. The contract also includes a 20-year Active Output Management (AOM 5000...
Read moreVestas Wind Systems has been commissioned to provide turbines for the project. The contract signed also includes a 15-year Active Output Management 5000 (AOM 5000) service agreement. The turbines are...
Read moreVestas has signed a EUR35.8 million (US$42.1 million) deal to provide turbines for the project. Delivery is scheduled for 2019. The project is expected to commence operations by 2019
Read more