RWE signs grid connection agreement for 1 GW Offshore wind farm in Denmark

Subscribe to our newsletter and get the latest news and business opportunities in your inbox
RWE signs grid connection agreement for 1 GW Offshore wind farm in Denmark

RWE has signed a grid connection agreement with the Energinet for its 1 GW Thor Offshore Wind Farm located off the Danish west coast approximately 22 kilometers from the port of Thorsminde. The agreement regulates the technical setup, the power quality and the cooperation between RWE and Energinet, at the point of connection (POC) in Volder Mark

To connect the offshore wind farm to the grid, Energinet will construct a new 220 kilovolt (kV) station as part of the 220/400 kV conversion of the existing 400 kV station in Idomlund. From there, 28 kilometers of cables will be laid underground to connect to a new 220 kV station (POC) located 4 km from the coastline. At Volder Mark the electricity generated by the offshore wind farm will be delivered to the grid. 

The 1,000 MW wind project will be Denmark’s largest offshore wind farm to date. It will have the capacity to produce enough electricity to supply the equivalent of more than 1 million Danish households. The project is expected to be fully operational in 2027.

Share this news

Join us

In order to get full access to News section, you must have a full subscription. You can check all the benefits of becoming a member and purchase a subscription on our membership page.