Prime Capital AG has started the full operation of its Stavro wind farm project located in northern Sweden. The project adds 62 turbines that produce a total capacity of 254 MW to the energy transition.
Consisting of two adjacent wind power plants in the areas of Blodrotberget and Blackfjallet, northwest of the Swedish city of Umea, the Stavro project will operate under corporate power purchase agreements (PPAs) with Google LLC and Swedish forestry and paper company Holmen AB.
NTR has signed a power purchase agreement (PPA) with Microsoft for 86 MW Norra Vedbo wind farm located in Jönköping, southern Sweden. Norra Vedbo will consist of 20 Vestas V...
Read moreOctopus Renewables Infrastructure Trust plc (ORIT) has signed a 10-year power purchase agreement with an unnamed off-taker for the energy output of the 48 MW Ljungbyholm wind farm in Sweden. Loc...
Read moreMEAG is financing the 750 MW Önusberget onshore wind farm, currently under construction, in Northern Sweden. The project is owned by renewable energy funds advised by the asset manager Luxcara....
Read moreGerman renewable energy developer wpd has contracted Nordex Group to supply turbines for the development of a 48 MW wind farm project in Sweden. Nordex will be supplying eight N163/5....
Read moreOX2 has agreed to acquire from RWE Renewables Sweden the rights to build the Riberget wind farm in the municipality of Ljusdal, Gävleborgs County, Sweden. Under the agreement, OX2 will acquire 1...
Read more