Mytilineos secures EPC contract for 100 MW Tutly solar project in Samarkand

Subscribe to our newsletter and get the latest news and business opportunities in your inbox

MYTILINEOS S.A., through its Renewables and Storage Development (RSD) Business Unit, has been selected by Total Eren for the engineering, procurement & construction (EPC) of the Tutly solar project in Uzbekistan.

Specifically, the RSD Business Unit undertook a turn-key contract which includes the Engineering, Procurement, and Installation of the PV plant and the High Voltage Substation. The technology for use includes a single-axis tracking system (3.644 trackers), string inverters (625 inverters), and bifacial modules (about 295.000 pcs). The grid connection is through a 220 kV high voltage line through a MV/HV substation of 35kV/220kV including 2x100MVA step up Transformers.

Once completed, the power plant is expected to produce 270 GWh per year, enough to supply the needs of about 140,000 people in Uzbekistan while reducing CO2 emissions by 160,000 tons per year.