KenGen construction progress of Olkaria V geothermal project

Subscribe to our newsletter and get the latest news and business opportunities in your inbox

Kenya Electricity Generating Company PLC, (KenGen) has made considerable progress in the construction of 165.4 MW Olkaria V Geothermal Power which project is spread across three contracts namely; Lot I -Steamfield development, Lot II-Power Plant and Lot II – High Voltage sub-station and transmission lines. The project will cost USD 450 million.

Construction contracts have been financed through a combination of KenGen’s internally generated funds and a loan facility from Japan International Corporation Agency (JICA) that was signed in March 2016.

The project is being implanted under the various EPC (Engineering, Procurement and Construction) contracts whereby most of the design and engineering is complete while most key equipment has been procured and are at different stages of assembly on site. KenGen completed the drilling of the geothermal wells that will supply steam to drive the power plant in 2016. The power generated at the plant will be evacuated through high voltage power lines from Olkaria to Suswa sub-station.

The commissioning of Olkaria V will lead to a total installed capacity of geothermal power for KenGen to 699 MW The construction of Olkaria V is in line with KenGen’s strategy for harnessing affordable and renewable baseload energy in support to the country’s energy needs and the required enabler for the Big Four growth pillars of food security, affordable housing, manufacturing and affordable healthcare.

The projects is divided into four lots- consultancy services, procurement and construction of steamfield, engineering, procurement and construction of the power plant, engineering, construction and procurement of high voltage substations and transmission lines

Construction of the power plant, which comprises two units, began in January 2017 and is set for commissioning in July 2019. The two units are under construction by the Consortium of Mistubishi Corporation, Mitsubishi Hitachi Power Systems Ltd and H-Young & Company E.A Limited.

KenGen, East Africa’s largest energy producer, plans to deliver steam for Unit one by January 2019 and for Unit two by April 2019.

Commercial operation of Unit one (82MW) has been scheduled for mid-April while that for Unit two is set for July 2019. Also in the pipeline is Olkaria 1 Unit 6 (83MW).

Share this update