Hallett Battery Storage Project Moves Forward into Construction Phase After Financial Close

Subscribe to our newsletter and get the latest news and business opportunities in your inbox

EnergyAustralia’s 50 MW/245 MWh Stage 1 Hallett battery energy storage system (BESS), co-located with a gas-fired power station, has reached financial close and is moving into the delivery phase.

The project, situated 210 km north of Adelaide, will later expand under the already-approved Stage 2 with an additional capacity of 150 MW/600 MWh. The first stage will deliver five hours of energy storage and progress from the planning phase to a final investment decision in less than two years. Construction is scheduled to begin in Q2 of 2026, with commercial operations anticipated to commence by mid-2027. The battery will be integrated using the existing infrastructure at the Hallett Power Station, reducing the requirement for additional transmission upgrades and limiting land use and environmental effects. Working alongside the current 235 MW gas-fired power station, the battery will enhance the site’s function as a flexible energy centre by delivering rapid and adaptable storage to support renewable energy, while allowing the gas facility to continue supplying reliable power during extended periods of high demand.

Italy-based battery system integrator NHOA Energy will supply batteries and inverters, while South Australian engineering, procurement and construction (EPC) company Enerven will deliver civil, electrical and construction works.

List of the country updates

Country updates

  • January 13, 2026

    Origin Energy’s First Stage of 700 MW/3,160 MWh Eraring BESS Commences Commercial Operations

    Origin Energy, together with contractor partners including Wärtsilä, Enerven, Jacobs, Lumea and Transgrid, has successfully commissioned and begun commercial operations of the first stage of...

    Read more
  • December 22, 2025

    ACCIONA Appointed to Build Western Renewables Link Transmission Project in Australia

    ACCIONA has been awarded the contract to construct the Western Renewables Link, a major new high-voltage transmission line in the state of Victoria, Australia. Together with its joint-venture partner...

    Read more
  • December 11, 2025

    Commercial Operations Started for 480 MW Solar Farm in Australia

    ACCIONA Energía has successfully completed the commissioning and start of commercial operations of the Aldoga Solar Farm (480MWp), located approximately 20 km north-west of Gladstone on th...

    Read more
  • November 24, 2025

    Construction contract awarded for 300 MW Solar Farm and Battery facility in Australia

    GHD, a leading global professional services company, has been appointed by Octopus Australia (OA) to deliver construction management services (CMS) for the Blind Creek Solar Farm and Battery

    Read more
  • November 19, 2025

    240 MW/480 MWh BESS Project becomes operational in Australia

    Australian electricity transmission network operator Ausnet has successfully energised the 240-MW/480-MWh battery energy storage system (BESS) on Victoria’s Mornington Peninsula.

    Read more