Government of Botswana approves EIA for 500 MW coal-fired power project

Subscribe to our newsletter and get the latest news and business opportunities in your inbox

African  Energy  Resources Ltd (AFR) has announced  that  the  Department  of Environmental Affairs of the government of Botswana has approved an updated Environmental Impact Assessment (EIA) for the Sese Power Project to allow up to 500 MW of power generation and the associated coal mining and coal processing activities. 

This is subject to the standard conditions of such approvals in Botswana, including a requirement that the project be  implemented within two years.

This marks an important milestone for the project as it will allow for the development of two 225 MW units, rather than two  smaller, less efficient 150 MW units as contemplated under the original EIA approval. 

AFR owns a 35% interest in the Sese Power Project. First Quantum Minerals Ltd (FQM) is the majority owner, as the project will export power to the company's Zambian copper operations.

The partners are currently implementing the resettlement action plan (RAP) around Sese, under which 25 households have to date had their grazing rights, water bores and access trails relocated to outside the Land Rights Lease. Resettlement of a further three households is required to complete this process.

AFR and FQM are also negotiating with the Botswana Energy Regulatory Authority for a Generation and Export License for the project, and with the Botswana Power Corporation for a Grid Connection and Use of System agreement. In addition, the developers are negotiating with other credit‐worthy offtakers for the remaining 88 MW of power available  from development of the first 225MW unit at Sese. 

List of the country updates

Country updates

  • February 19, 2018

    The Ministry of Mineral Resources, Green Technology and Energy Security has requested that the RFP be re-tendered, and has invited Tlou Energy to submit the project under a new re-tender process

  • February 11, 2018

    The project has been put on-hold after the disagreement of terms with the energy ministry

  • November 02, 2017

    Botswana government is going to support Marubeni and POSCO for the development of the project

  • September 20, 2017

    Tlou Energy has submitted the project to a Request for Proposals (RFP) for the development of up to 100 MW of CBM power in Botswana, issued by the Ministry of Mineral Resources, Green Technology and Energy Security

    Tlou Energy has submitted the project to a Request for Proposals (RFP) for the development of up to 100 MW of CBM power in Botswana, issued by the Ministry of Mineral Resources, Green Technology and E...

    Read more
  • August 31, 2017

    Botswana Power Corporation receives 166 EOIs for 100 MW solar project

    Read more

Share this update