The project was dicussed in the House of Commons, the elected chamber of the UK Parliament, with Members urging the government to approve the project. The Junior Wales Minister avoided saying when the approval would be granted
Statoil announced all the wind turbines have been installed. The company also informed the project was completed below the budget of GBP 1.5 billion