Wind turbine commissioning is the last stage before the completion of an offshore wind farm. Before the commercial operation, each wind turbine needs to go through a power generation test lasting between 10 to 14 days to complete the commissioning stage. The 20 wind turbines for the second phase of Formosa 1 are expected to be fully operational within the next two months.
The Formosa 1 offshore wind farm includes two phases: two 4MW wind turbines were installed in October 2016 for the first phase and officially entered commercial operation in April 2017. The second phase involves the installation of 20 6MW wind turbines. Formosa 1 is located approximately 2-6km off the coast of Miaoli County. The total power generation capacity for Formosa 1 is 128MW, enabling it to supply 128,000 Taiwanese households with clean renewable energy.