E.ON has announced that it is partnering with GE to repower its Panther Creek I and Panther Creek II wind farms in West Texas. The repowering includes the replacement of a significant portion of the wind farm components, effectively increasing the annual production for all 172 wind turbine generators (WTGs) totaling 258 MW on the sites.
The erection and commissioning of the project will be conducted by GE as part of the equipment delivery contract and is expected to be complete in Q3 2019.
Panther Creek I came online in September 2008 and consists of 95 GE 1.5 MW SLE turbines for a total of 142.5 MW. It is the first of a three-phase project in West Texas and is located in Howard and Glasscock counties.
Panther Creek II came online in December 2008 and consists of 77 GE 1.5 MW SLE turbines for a total of 115.5 MW. Its footprint spans parts of Glasscock and Sterling counties, Texas.
First Solar has announced that Facebook has signed a power purchase agreement (PPA) with PacifiCorp for the 58 MWAC Cove Mountain Solar Project, located near Enterprise,...
Read moreFirst Solar, Inc. and Origis Energy USA have announced that Origis Energy has acquired the GA Solar 4 Project from First Solar. The 200 MWACphotovoltaic solar generation asset, located in Twiggs Count...
Read moreInnergex Renewable Energy Inc. has announced the acquisition of a prospective solar project of approximately 260 MW (DC) from developers Open Road Renewables and MAP Renewable Energy.&n...
Read moreAqua America Inc., a regulated water and wastewater utility, announced it will acquire Peoples in an all-cash transaction that reflects an enterprise value of US$4.275 billion, which includes th...
Read moreEDF Renewables North America and Ameren Missouri, a subsidiary of Ameren Corporation, have announced an agreement by which Ameren will acquire, after construction, the 157 MW ...
Read more