Construction of the $560 million Dundonnell Wind Farm is scheduled to begin by the end this week. Aus Net Services will shortly begin work on the transmission line.
Construction will take about 22 months and the transmission line about 14 months. Dundonnell Wind Farm will be one of the largest in the State and once operational, will employ 10 full-time staff.
The 336MW wind farm will produce enough clean energy each year to power about 245,000 homes and save the emission of roughly 1.3 million tonnes of carbon. This is the equivalent of removing about 440,000 cars from our roads.
It will incorporate 80 turbines with a blade tip height of 189 metres. There will be an onsite quarry and concrete batching plant, with 33kV underground cables between the turbines and 38 kilometres of 220kV overhead transmission line and a new substation.
There are 12 host landholders over about 4500 hectares across the total project site.
The New South Wales Planning Commission has approved with conditions, changes to the state planning approval for the Coppabella Wind Farm located in Yass Valley in NSW Southern Tablelan...
Read moreTempo Australia Ltd has been commissioned by Enel Group to develop the 34.2 MW Cohuna solar photovoltaic project located in Gannawarra, Australia. The engineering and construction contract...
Read moreA year after construction began in March 2018, BayWa's two wind farms located at Timboon West and Yawong has been inaugurated. The project sites are amongst the windiest in the state of Victoria...
Read moreGlobal law firm White & Case LLP has advised a group of international lenders on a two-tranche long term debt refinancing of the 50 percent interest in Macarthur Wind Farm in Victoria, Australia,...
Read moreThe consortium developing the East Rockingham Resource Recovery Facility has awarded SUEZ the role of waste management partner for the project for a minimum term of 20 years. The consortium of Hitachi...
Read more