Jointly developed by Mitsui & Co.Northland Power Inc, and Gentari International Renewables, the Hai Long Offshore Wind Project ("Hai Long Project") announced the successful offshore installation of the first wind turbine for the Hai Long 3 wind farms. 

The nacelle of the turbine installed was assembled locally at Siemens Gamesa’s nacelle assembly facility in Taichung. The offshore installation was carried out by CDWE, Taiwan’s leading large-scale offshore wind marine engineering contractor. This seamless integration of local assembly and offshore installation represents substantial progress in deep-rooting offshore wind technology within Taiwan.

Reviewing the construction progress: the Hai Long 2A wind farm, featuring 21 turbines, was completed and grid-connected at the end of last year. Hai Long 2B also installed all 16 turbines last year. With today’s installation of the first turbine at Hai Long 3, the project has officially entered its crucial construction phase. 

Beyond driving national renewable energy targets, the Hai Long Project is actively fulfilling its localization commitments. Regarding nacelles, building upon the mandatory requirements for Hai Long 2A, the project expanded its partnership with Siemens Gamesa to include Hai Long 2B and 3 wind farms in its local procurement. A total of 73 locally assembled nacelles completed assembly this month and are currently being transported offshore for installation. 

List of country news

Country news

  • March 12, 2026

    LAUTEC Selected for QA/QC and HSE Services on 495 MW Offshore Wind Farm in Taiwan

    LAUTEC has been awarded the Framework Consultancy Agreement for Site QA/QC and HSE resources on the Formosa 4 Offshore Wind Farm in Taiwan by Synera Renewable Energy (SRE).

    Read more
  • February 09, 2026

    CAPE Holland Awarded Contract for 500 MW Offshore Wind Farm in Taiwan

    CAPE Holland is pleased to announce that it has secured a contract with CDWE for the 500 MW Fengmiao Offshore Wind Farm project in Taiwan.

    Read more
  • January 21, 2026

    All Turbines installed for 920 MW Offshore Wind Farm in Taiwan

    The installation of the last wind turbine at the 920 MW Greater Changhua 2b and 4 offshore wind farms in Taiwan was completed last week.

    Read more
  • January 05, 2026

    495 MW Offshore Wind Farm in Taiwan Fully Subscribed via CPPA

    Synera Renewable Energy Group (SRE) has announced that all 495 MW of capacity for its Formosa 4 offshore wind project in Taiwan has now been fully sold through long-term corporate power purchase agreements.

    Read more
  • December 10, 2025

    PPA signed for a 495 MW Offshore Wind Farm in Taiwan

    Synera Renewable Energy Group (SRE Group) has announced that its Formosa 4 Offshore Wind Project has signed a long-term corporate power purchase agreement (CPPA) with Taiwan Smart Electricity & Energy (TSEE).

    Read more

Share this news

Join us

In order to get full access to News section, you must have a full subscription. You can check all the benefits of becoming a member and purchase a subscription on our membership page.