Construction starts on world’s largest offshore wind farm

Subscribe to our newsletter and get the latest news and business opportunities in your inbox
Construction starts on world’s largest offshore wind farm

Construction on the world’s largest offshore wind farm has started near the coastal village of Ulrome, East Riding of Yorkshire, England. Dogger Bank Wind Farms, a joint venture between SSE Renewables and Equinor, is made up of three offshore wind farm sites in the North Sea, totaling 3.6 gigawatts (GW): Creyke Beck A (1.2 GW), Creyke Beck B (1.2 GW) and Teesside A (1.2 GW). All three sites were successful in the UK’s September 2019 Contracts for Difference (CfD) auctions.

The wind farm will make use of the world’s most powerful turbine, GE’s Haliade-X, and will be capable of generating enough renewable energy for over 4.5 million homes each year.

Jones Bros Civil Engineering has been awarded the contract to install the onshore cable infrastructure for the Creyke Beck A and Creyke Beck B sites. The works will also involve completing bulk earthworks at the onshore HVDC convertor station locations in East Riding.

The onshore infrastructure includes the installation of approximately 20 miles of electrical cables within ducts. The ducts will be installed within trenches and where required via drilling under existing infrastructure and natural obstacles.

The completed onshore cable will transport the power generated by the two offshore wind farm sites, Creyke Beck A and Creyke Beck B from the landfall point at Ulrome to the new convertor stations (one per project) in the south of Beverley. The cable route will connect to the existing National Grid substation at Creyke Beck, Cottingham.

The works contract also includes vegetation clearance, preparing access junctions and construction of a temporary access road to facilitate the main works, and installation of pre- and postconstruction land drainage.

The full works are expected to take approximately two years to complete.

Steve Wilson, Managing Director of Dogger Bank Wind Farms, said: “Dogger Bank Wind Farms will play a critical role in the UK’s effort to achieve net-zero through the use of low-carbon fuel sources and we’re incredibly pleased to work with one of the UK’s leading civil engineering contractors, Jones Bros, as we commence construction and start delivering Dogger Bank.”

Share this news

Join us

In order to get full access to News section, you must have a full subscription. You can check all the benefits of becoming a member and purchase a subscription on our membership page.