The jacket for the offshore substation for the wind farm, constructed by Smulders, is on its way to the project site. It will be installed on 7 or 8 June. The structure was loaded out on 21 May
Read moreSnowy Hydro, an end-to-end electricity provider in Australia, has published a Request for Expressions of Interest (RFEOI) for the supply of long-term offtake arrangements from renewable energy so...
Read moreNew South Wales' Department of Planning and Environment has approved the construction of the project. Construction is expected to start in the third quarter of 2018 and to be completed in up to 12 months
Van Oord has been awarded a EUR500 million (US$582 million) contract to design, manufacture and install the 80 foundations for the project. The first foundations will be ready to install in early 2020
Southern Power has acquired the project from Renewable Energy Systems Americas Inc (RES) and Vestas Wind Systems. The project is expected to be finalised in the final quarter of 2019