NorthWind official takes over the operation of Phase II of the wind power plant from the contractor and wind turbine supplier, Vestas of Denmark
January 15, 2008
Mobilization and start of civil works construction for Phase II
December 30, 2007
Loan in the amount of US$13.10 million to Finance Phase II of the project was signed between NorthWind and ABN Amro and Nordea Bank
November 15, 2007
Draft EA Report released for consultation
November 15, 2007
EnCana has entered into an agreement with SBM for the development and operation of the Deep Panuke production field centre