The Texas municipality-owned utility, New Braunfels Utilities (NBU), has signed a 15-year power purchase agreement (PPA) deal for the 100 MW solar power capacity of the 255 MW Long Draw Solar project in Texas.
NBU has signed a tariff for the project for US$25 per MWh.
The project is expected to commence operation by June 2020.
Tri-State Generation and Transmission Association has announced the development of a new solar project in partnership with Juwi Inc. The 100 MW Spanish Peaks Solar Project is Tri-State’s second...
Read moreInvenergy, a privately-held developer and operator of sustainable energy solutions, has announced that it completed construction financing on December 19, 2018 for the 160 megawatt Southern Oak Solar...
Read moreInvenergy has announced that it has completed construction financing for its 302.4 MW Santa Rita East Wind Farm, located approximately 70 miles (113km) west of San Angelo, Texas.
Read moreApex Clean Energy has announced the purchase of 442.5 MW of solar projects located across the eastern US state of Virginia from renewable energy developer SolUnesco.
Read moreEnergias de Portugal S.A. (EDP) has announced that EDP Renováveis, S.A. (EDPR), 82.6% controlled by EDP, has closed an agreement to sell an 80% equity shareholding in a portfolio...