Ørsted has signed a EUR175 million(US$200.35 million) 8-year loan agreement with the Nordic Investment Bank (NIB) for the purpose of co-financing its investment in the Borssele 1 & 2 Offshore Wind Farm located off the coast of Zeeland, in the south-west of the Netherlands.
Together with the EUR500 million (US$572.42 million) loan agreement closed with the European Investment Bank on 6 September 2021, the intended long-term financing of Ørsted’s investment in the Borssele 1 & 2 project is now complete. The two wind farms have a total of 94 units of 8 MW Siemens Gamesa 8.0-167 DD wind turbines generating 752 MW of power, which is enough electricity to meet the needs of around one million domestic households.
The Offshore Wind Farm delivered the first power to the Dutch grid in April 2020 and was fully commissioned in December 2020.
In May 2021, Ørsted completed a 50% divestment of the Borssele 1 & 2 project to Norges Bank Investment Management.
Worley has been awarded an early engineering services contract by Shell to support the development of a new 200 megawatt electrolysis-based hydrogen plant in the Netherlands.
Read moreØrsted has signed an agreement with Norges Bank Investment Management (NBIM), who will be acquiring a 50 % ownership share of Ørsted's 752 MW Borssele 1 & 2 Offshore Wind Farm.
Read moreWindpark Fryslân has started building wind turbines for 382.7 MW Fryslan nearshore wind project in the IJsselmeer. From March to June 2021, the 89 wind turbines will be shipped, installed and tested.
Read moreThe offshore wind complex Borselle III and IV with a combined capacity of 731.5 MW has started its commercial operation in the North Sea, off the coast of the Netherlands.
Read moreSiemens Gamesa Renewable Energy and CrossWind have executed the contract to deliver the turbines for the 759 MW Hollandse Kust Noord offshore wind park in Netherlands.