The State of New Jersey is set to launch the second round of offshore wind projects tender of about 1.2 GW capacity in September 2020 following the launched 1.1 GW tender in 2018.
The State plans to meet the 7.5 GW offshore wind generating capacities by 2035. There will be four more rounds by 2022, 2024, 2026, and 2028.
Solicitation Round |
Target generating capacity (MW) |
Issue date |
Submittal date |
Award date |
Estimated date of commercial operation |
1 |
1,100 |
Q3 2018 |
Q4 2018 |
Q2 2019 |
2024 |
2 |
1,200 |
Q3 2020 |
Q4 2020 |
Q2 2021 |
2027 |
3 |
1,200 |
Q3 2022 |
Q4 2022 |
Q2 2023 |
2029 |
4 |
1,200 |
Q2 2024 |
Q3 2024 |
Q1 2025 |
2031 |
5 |
1,400 |
Q2 2026 |
Q3 2026 |
Q1 2027 |
2033 |
6 |
1,400 |
Q1 2028 |
Q3 2028 |
Q1 2029 |
2035 |
WEC Energy Group has agreed to increase its ownership interest from 80% to 90% in 750 MW USA Midwest wind portfolio: 250 MW Blooming Grove Wind Farm in Illinois; 300 MW Thunderhead Wind Energy Center...
Read moreLongroad Energy has completed the acquisition of four solar projects that have a combined capacity of 160 MWac from Frist Solar. Longroad Energy is a US-based renewable energy developer, owner,...
Read moreCIM Group has launched the construction of Westlands Solar Park (WSP), one of the largest permitted solar parks in the world that could grow to more than 2,700 megawatts (2.7 gigawatts) of renewable e...
Read morePeyton Creek Wind Farm, a 151 megawatt (MW) onshore facility located in Matagorda County, Texas, has achieved commercial operation. The project is powered by 48 Nordex 3.15 MW turbines and can generat...
Read moreArcLight Capital Partners, LLC has entered into an agreement to acquire 100% of the ownership interests in Griffith Energy LLC from Star West Generation LLC, a portfolio company of funds managed by Oa...
Read more