Valley Clean Energy (VCE) has entered into a 15-year solar-plus-storage PPA with Leeward Renewable Energy in the USA. The PPA involves the 72 MW photovoltaic solar project with a 36 MW battery storage capacity.
Located in Kern County, California, the Willow Springs 3 project will supply electricity to 27% of VCE’s 125,000 customers in Yolo County. Construction will begin in December 2021, and the project is expected to start energy delivery to Valley Clean Energy by December 2023.