Vestas has secured a firm order for the 257 MW Arcadis Ost 1 offshore wind project from Parkwind, to deliver 27 V174-9.5 MW turbines 19 km northeast off the coast of the island of Rugen, in the German Baltic Sea.
The V174-9.5 MW turbines will be installed using a floating installation method, an industry-first, instead of the typical method using a jack-up vessel. In collaboration with Parkwind and the vessel operator, Heerema Marine Contractors, a dual crane vessel will be used which enables the floating installation method, involving dynamic lifting and installation of all turbine components. The innovative installation method prevents challenges with seabed and soil conditions by avoiding contact with the seabed altogether and therefore reduces project risk by allowing faster installation time, contributing to reducing the levelised cost of energy for the project.
Nils de Baar, President of Vestas Northern & Central Europe, said: “The floating installation method we are utilising will potentially be a gamechanger for installing projects in deeper waters, saving time and further reducing the cost of offshore wind. Projects like Arcadis Ost 1 will continue to deliver on Germany’s offshore wind ambitions, to reach 20 GW of installed wind by 2030”.
Once installed, Vestas will also service Arcadis Ost 1 with a 15-year service contract.
Turbine components will be delivered to the Port of Roenne on the Danish island of Bornholm, starting in the third quarter of 2022. Offshore installation is expected to commence by the end of 2022 and Arcadis Ost 1 is planned for full operation in 2023.