ReNew Power has commissioned the 250 MW capacity of its Interstate Transmission System (ISTS) solar generation project, SECI-3. The project has a total generation capacity of 300 MW which was won by ReNew Power in tranche 3 of the competitive auction conducted by the Solar Energy Corporation of India (SECI). ReNew expects the remaining 50 MW capacity to be commissioned by the end of September 2021.
This solar project is in the Jaisalmer district of Rajasthan and has a 25-year Power Purchase Agreement (PPA) with SECI and will provide clean electricity to the state of Bihar at a rate of INR2.55/kWh (US$0.035). The project is also expected to provide direct employment to around 600 people.
In this project, ReNew will install monocrystalline modules with fixed tilt and string inverters which enhance the project efficiency. ReNew will also be using robotic module cleaning at this site to help conserve water in the desert state of Rajasthan.