Ørsted has started constructing its first offshore wind farm in the Netherlands by installing the first foundations at the 752 MW Borssele 1 & 2 offshore wind farm.
Borssele 1 & 2 is located 22 kilometers off the coast of the Dutch province of Zeeland, in the south-west of the Netherlands. At water depths ranging from 14 to 39.7 meters, a total of 94 monopile foundations will be installed at the wind farm. Starting in April, the 94 Siemens Gamesa 8 MW wind turbines will be installed. The wind turbines will generate enough electricity to meet the needs of around one million domestic households.
The monopiles and transition pieces for Borssele 1 & 2 have been fabricated by Sif, EEW SPC, EEW OSB and Bladt Industries. All foundations will be installed by DEME.
Henrik Egholm, EPC Director for Borssele 1 & 2, says: "It's great that the installation has started now, according to plan. We're very well on track with the construction of the wind farm. Borssele 1 & 2 will be operational by the end of this year."
Jan Wind, Senior Project Manager for Borssele 1 & 2, elaborates: "The first monopile installed was also the heaviest and tallest on the wind farm, weighing 1,188 tons and measuring 76 meters. The diameter at the bottom of the foundation is 8.5 meters, wide enough to hold a football goal."
Steven Engels, General Manager for the Netherlands, says: "Borssele 1 & 2 will be our first offshore wind farm in the Netherlands and is an important step in the Dutch government's ambitious shift towards green energy. Once completed, Borssele 1 & 2 will be the largest offshore wind farm in the Netherlands, able to supply renewable power to around one million Dutch households."
Vattenfall and Siemens Gamesa Renewable Energy have agreed to extend the Hollandse Kust Zuid turbine supply to include zone one and two in addition to three and four.
Read more
Mitsubishi Corporation (MC) and Chubu Electric Power Co., Inc. have been selected as the preferred buyers in a bid for the Dutch Energy Company Eneco. Through their joint establishment of a special purpose company in the Netherlands called Diamond Chubu Europe B.V., MC and Chubu expect to acquire up to 100% of Eneco’s shares at a value of EUR4.1 billion (US$4.5 billion).
Read more
Prysmian Group has completed the HVDC test on the 700 MW submarine interconnector COBRAcable that links The Netherlands and Denmark. COBRAcable is a very innovative and tight schedule turn-key project, standing out for its big cross-sections and the various construction methods and installation technologies used.
Read more
Siemens Gamesa Renewable Energy has reached an agreement to acquire selected European assets of Senvion Group for EUR200 million (US$223 million).
Read more
The near-shore Windpark Fryslân to be located on the Ijselmeer lake, near Breezanddijk, the Netherlands with a 383 MW capacity has reached financial close.
Read more